Business Performance 2006/07

Our output performance measures reflect the aims that were set out in the ODPM’s (now CLG) 'Sustainable Communities Plan, Homes for All' and the government’s Public Service Agreement (PSA) targets. These cover:

  • brownfield land reclaimed
  • housing units – starts on site commissioned
  • housing units – completed
  • employment floorspace created
  • private-sector investment attracted.

2006/07

In May 2006 we published a set of quality standards to be applied to all our projects and these are reported in the table below insofar as they relate to our output achievements over the past two years.

Outputs from all approved projects1

Output 2005/2006 2006/2007
Lower Target2 Upper Target2 Outturn3 Lower Target2 Upper Target2 Outturn

Brownfield land reclaimed (ha)

230

240

243

270

310

328

Housing units facilitated (starts on site commissioned)

5,040

6,070

7,615

8,490

9,560

9,403

Housing units facilitated (completions)

2,460

2,520

3,2224

3,990

4,490

4,2485

Employment floorspace created (‘000 sq m)

250

270

4196

260

300

3267

Private sector investment (£m)

480

500

677 8

870

980

1,0229

 

National Coalfields Programme

The total outputs include those relating to the National Coalfields Programme, delivered through close co-operation with the relevant Regional Development Agencies. In 2006/2007 the outputs delivered on these former colliery sites amounted to:

  • 217 ha of brownfield land reclaimed
  • 274 housing starts on site commissioned
  • 398 housing units completed
  • 77,982 sq m of employment floorspace created
  • £182m of private sector investment attracted.

The Housing Partnership

In addition, as a result of our collaboration with the Housing Corporation through The Housing Partnership (THP), 166 housing starts on site were commissioned and 520 housing units were completed.

 